The Western Queen Gold and Tungsten Project is located 90km northwest of Mt Magnet within Western Australia’s Yalgoo Mineral Field. The project is 100% owned by Rumble Resources and comprises two mining leases M59/45 and M59/208, one miscellaneous licence L59/40 and two exploration licences E20/967 and E59/2816.

Western Queen is strategically located 180km from Gylden’s, Kirkalocka (2.0 Mtpa) plant where Western Queen ore will be treated.
The Western Queen Deposits are typical Yilgarn shear zone gold systems. Steeply dipping to the west, the gold is hosted in sheared silica-sulphide zones within a geology of intercalated amphibolies of mafic to ultramafic composition.
Western Queen sits on a major regional shear system that remains largely untested along strike and at depth, presenting strong exploration upside. Historical production from the Western Queen Central and South pits totals 880,000 tonnes at 7.6 g/t Au for 215,000 ounces, with the Central pit alone producing 660,000 tonnes at 8.9 g/t Au for 189,500 ounces.
Conceptual underground mine design to mine Western Queen South and Central from the October 2026 Updated Scoping Study.
Western Queen Central - long section showing drillhole locations and gold grade-thickness contours.
Western Queen South - Cross Section of Geology and Resource Estimate Block Model coloured by grade.
GOLD
Gold Resources at Western Queen

Mineral Resources reported on a dry in-situ basis
In October 2026, Rumble reported an optimised Mineral Resource Estimate to 393koz including Indicated Resources of 223.8koz.
TUNGSTEN
In August 2025 Rumble reported a maiden Tungsten Mineral Resource Estimate at Western Queen of 4.31Mt @ 0.31%WO3 for 13.2kt of WO3.
Tungsten Resources at Western Queen

Mineral Resources reported on a dry in-situ basis
ORE TOLL MILLING & BLENDING AGREEMENT
In May 2026 the Company signed an agreement with Glyden Resources to treat Western Queen ore at Glyden’s Kirkalocka plant. The agreement runs for approx. 5 years from the processing of first ore through Kirkalocka.
MINE DEVELOPMENT – SCOPING STUDY
The Updated Western Queen Scoping Study (the “Scoping Study” or “the “Study”) was completed in October 2026.
The Study is based on mining both Western Queen South and Central Resources from underground and processing the ore at the Kirkalocka plant approximately 180km’s south east of Western Queen.
Key findings from the Western Queen South Scoping Study are as follows:
MOVING TOWARDS PRODUCTION
The next steps to get Western Queen into production are:
EXPLORATION
The most recent drilling program, resulted in the June 2026 Resource Estimate Upgrade from 370koz to 433.6koz, including a 54% increase in Indicated Resources to 227koz and the discovery of the 52.5koz high-grade zone at Western Queen Central. Planning for the next drill program is underway.
The June 2026 Resource Estimate was optimised for underground mine development which resulted in an increase in the average grade to 3.1g/t and contained gold of 393koz as reported in the 28 October 2026 Western Queen Mineral Resource Estimate.